San Manuel Casino Box Culvert & Storm Drainage

    San Manuel Casino Box Culvert & Storm Drainage

    • Location: Sand Creek Channel, CA
    • Agency: Perini Building Company
    • Project Value: $1,902,781.00

    Project Description

    Reyes Construction will install a 20 x 20 high concrete box culvert at the South Crossing. The scope of work includes the demolition and disposal of the existing South Crossing structure; rail and wire revetment; unusable rock and boulders; unsuitable backfill soil; any grout and cement within the channel; and any existing fencing. Reyes Construction will also clear and grub, provide shoring, pre-mold joint fillers, gates, etc., as well as provide erosion control, channel water diversion and pumping. 24 RCP piping and connections were installed in 10 locations to include building tie-ins. Additionally, the existing bridge was removed.