Intersection Bridge & Improvements, MCB Camp Pendleton, CA

    Intersection Bridge & Improvements, MCB Camp Pendleton, CA

    • Location: MCB Camp Pendleton
    • Agency: U.S. Navy
    • Project Value: $12,538,670.00

    Project Description

    Reyes Construction was awarded the new intersection bridge serving the Lincoln Housing area on Wire Mountain Road and Camp Del Mar at Vandergrift Blvd is located close to the main gate entry for MCB Camp Pendleton.

    The first phase of construction  involved relocation of buried utilities (especially electrical links) around the planned bridge. The work also included new connections between Del Mar Road and Vandergrift Boulevard and between Wire Mountain Road and Vandergrift Boulevard — both of these new intersections are equipped and follow the planned access ramps to/from Vandergrift Boulevard. Phase 2 of construction involved constructing the elevated approaches to connect the new intersection bridge abutments to the existing Del Mar Road freeway overcrossing bridge and to the Wire Mountain Road approach. Phase 3 completed the new bridge and pavement across Vandergrift Boulevard between the new abutments and earth embankments. Phase 4 of the work involved completing the intersection, traffic signals and final connections to the entry/exit ramps for the Vandergrift Boulevard connections from the Del Mar Road bridge.