NCMT Berth 24-10 Structural & Mooring Repairs, Port of San Diego

    NCMT Berth 24-10 Structural & Mooring Repairs, Port of San Diego

    • Location: National City, CA
    • Agency: Port of San Diego
    • Project Value: $6,132,000.00

    Project Description

    The project is structural rehabilitation of the reinforced concrete marginal wharf and mooring repairs at Berth 24-10. Work will consist of removing the asphalt pavement and constructing a new concrete, cast-in-place deck over the existing concrete deck, driving pipe-pile over 59 existing pre-stressed concrete piles, placing 3 jackets on existing concrete piles, demolishing and replacing the cap/edge beam, replacing the existing 50-ton double bits and cleats with new 100 ton bollards, replacing fenders and ladders, replacing 750 lineal feet of potable water lines, pits risers, and vaults; replacing existing electrical utilities and switchboard electrical equipment, and installing a storm-water treatment system.